Rock Creek Bridge CRP 274:

2/2/10 Grout was approved last Wednesday. Girders were delivered on Friday morning. The final girders were placed by 11 am. The contractor is working on tying rebar and forming for the end walls, girder stops and diaphragms. They plan to pour concrete early next week. They may also start on embankment for the bridge approaches.

This contract provides for the improvement of Bickleton Hwy and Rock Creek Rd by construction of new 105 foot bridge over Rock Creek on Bickleton Hwy. Also the improvement of approximately 660-feet of roadway on Bickleton Hwy, approximately 275-feet of roadway on Rock Creek Rd, installation of guardrail, placement of rip rap protection, and other work.



You can download a free Acrobat Reader from the Adobe web site. download Adobe Acrobat Reader



Date of Source Material: 5/20/2009
Source: Klickitat County Roads

CONTENT INDEXES

Public Works Home   Road Programs   Construction Updates   2009 Construction Projects   Road Guide   Interactive Mapping Program   Surveys, Plats, Short Plats   Permit forms   Road Restrictions & Closures   Transportation Standards   Map sales   Public Notices: Public Works  

Contact:
Public Works Director
Gordon Kelsey, P.E.
Public Works Dept.
115 S. Golden St, MS-CH-19
Goldendale, WA 98620
Phone: 509 773-4616
Fax: 509 773-5713
Hours: Monday-Friday 8am-5pm

Top of Page