| Home > Public Works Home > Construction Updates > Construction Updates |
Construction UpdatesRock Creek Bridge CRP 274: 2/2/10 Grout was approved last Wednesday. Girders were delivered on Friday morning. The final girders were placed by 11 am. The contractor is working on tying rebar and forming for the end walls, girder stops and diaphragms. They plan to pour concrete early next week. They may also start on embankment for the bridge approaches. This contract provides for the improvement of Bickleton Hwy and Rock Creek Rd by construction of new 105 foot bridge over Rock Creek on Bickleton Hwy. Also the improvement of approximately 660-feet of roadway on Bickleton Hwy, approximately 275-feet of roadway on Rock Creek Rd, installation of guardrail, placement of rip rap protection, and other work.
| |
Date of Source Material: 5/20/2009 Source: Klickitat County Roads |
| CONTENT INDEXES Public Works Home Road Programs Construction Updates 2009 Construction Projects Road Guide Interactive Mapping Program Surveys, Plats, Short Plats Permit forms Road Restrictions & Closures Transportation Standards Map sales Public Notices: Public Works Contact: Public Works Director Gordon Kelsey, P.E. Public Works Dept. 115 S. Golden St, MS-CH-19 Goldendale, WA 98620 Phone: 509 773-4616 Fax: 509 773-5713 Hours: Monday-Friday 8am-5pm |